Connecting solar in Liverpool: SP Energy Networks, G98 and G99

Every solar system in Liverpool connects to a network run by SP Energy Networks, not by your electricity supplier. For most homes the process is a notification the installer handles. This guide explains the two routes, where batteries fit, and what you should end up holding.

Checked 3 November 2026. Written and published independently by SEO-DONS LTD.

Who runs the network

Your electricity supplier sells you power; the wires and substations belong to a separate company, the distribution network operator. In Liverpool, as across Merseyside, Cheshire and North Wales, that is SP Energy Networks. Solar panels feed into its network whenever they make more than the house is using at that moment, which is why it needs to know they are there.

Most houses have a single-phase supply. Some larger or newer homes have three phases, which raises the amount that can connect on the simple route; your installer will check which you have.

G98: tell, then confirm

Small generators connect under an industry standard called G98. SP Energy Networks says that for a single generator of less than 16 amps per phase, 3.68 kW, you must inform it of the proposal before or at the time of commissioning, which is a legal obligation under the Electricity Safety, Quality and Continuity Regulations 2002 (SP Energy Networks). The installation commissioning confirmation, with the final circuit diagram and test report, then has to reach it within 30 days, and it says it will not normally object to the connection if G98 and the law are followed.

The two connection routes for a Liverpool home
G98G99
SizeUnder 16 A per phase (3.68 kW single-phase)Above that, or several units together
Network involvementTold before or at commissioningApplied to, and must agree, before connection
Paperwork afterCommissioning confirmation within 30 daysAs set out in the network's agreement
Typical caseA small to medium roof system on its ownA large system, or solar with a battery taking the total over the limit

A 3 kW system on a south roof in central Liverpool would make about 2,895 kWh a year (our arithmetic from PVGIS) and sits comfortably within G98 on its own.

G99: ask first

Above the G98 limit, or where several generating units add up past it, the connection falls under G99, and the network operator has to assess and agree it before it is switched on. That can take time and occasionally leads to conditions or costs if the local network needs work. Ask any installer quoting a larger system whether it needs G99, who will apply, and how long their recent applications to SP Energy Networks took.

Batteries and export limiting

A home battery has its own inverter, and that counts towards the same limit. So a system that is comfortably within G98 on its own can cross it once a battery is added. Some designs use export limiting: controls that stop the system sending more than an agreed amount to the network at once. The network operator still has to accept the arrangement. The battery page covers sizes and costs, including the 2025/26 median of £890 per kWh for 6 to 11 kWh batteries (DESNZ).

The supplier side

The network connection and the money for exported power are separate matters. To be paid for exports you need a meter that records them, usually a smart meter, and an export tariff from a supplier, which may or may not be the company that sells you electricity; larger suppliers must offer one at a rate above zero (Ofgem). The supplier will ask for your MCS certificate. See export payments.

Papers to keep

  • A copy of the G98 notification or the G99 agreement.
  • The commissioning confirmation and test report.
  • The MCS certificate and electrical installation certificate.
  • Warranties for the panels, inverter, any battery and the workmanship.

Ask for them in the contract; the installer checklist lists them. For what the system will cost, see solar costs in Liverpool.

Grid questions from Liverpool

Do I need permission from SP Energy Networks for solar panels?

Not for a typical home system. Under G98, for a single generator under 16 amps per phase (3.68 kW on a single-phase supply), SP Energy Networks must be told before or at commissioning and sent a commissioning confirmation within 30 days. Larger systems need its agreement first under G99.

Who deals with SP Energy Networks, me or the installer?

The installer, in practice. They submit the notification or application and the test documents. Ask for a copy for your records, because a buyer's solicitor may ask for it later.

Does adding a battery change the connection?

It can. A battery's inverter counts towards the same limit as the solar inverter, so solar plus a battery can take a home above the G98 threshold and into the G99 route, unless the system is designed with export limiting the network accepts.

How long does a G99 application take?

It depends on the network's workload and what its assessment finds. Ask your installer how long their recent G99 applications to SP Energy Networks have taken, and plan the install date around it.

Where the facts come from

Further reading

Unsure which route your system needs?

Tell us the system size, any battery and whether the house is on a single-phase supply. SEO-DONS LTD, who publish this guide, write back by email.

What happens next

  1. SEO-DONS LTD, publisher of this guide, receives your message.
  2. We read it and write back by email.
  3. Nothing is signed or arranged by asking.